Wagner Road and Davies Road Intersection Closure
SECOND UPDATE: This work has been rescheduled to the evening of Friday, September 27.
UPDATE: This work has been rescheduled to the evenings of August 21, 22, 28 and 29.
EDMONTON, AB – June 28, 2019 – Starting on or about July 12, 2019, the intersection at Wagner Road and Davies Road will be closed overnight (9:00 p.m. to 6:00 a.m.)
This work is expected to take place on July 12 and July 23, 2019.
To accommodate this work, the public will be impacted in the following areas:
- During off-peak hours (9:00 p.m. – 6:00 a.m.) on the nights of July 12 and 23 the intersection at Davies Road and Wagner Road will be closed.
- Please visit takeets.com/generalservicealerts.com for all ETS changes and updates
During this time please watch for, and observe, all traffic detours and direction of construction personnel.
TransEd is committed to following all City of Edmonton bylaws and regulations and has obtained an overnight roadwork permit so that work can take place during nighttime hours in order to minimize major daytime traffic disruptions. *City of Edmonton Bylaw C14600.
Thank you for your understanding and patience as construction on the Valley Line LRT progresses. For the most current, up-to-date information in your area, please visit: https://transedlrt.ca/advisories/.
Please refer to the attached map for more details. For more information, visit our website https://transedlrt.ca/advisories or contact us via email at info@transedlrt.ca or by phone 780-224-0964.