LRT Bridge Span Installed Over Whitemud Drive

Notice

EDMONTON, AB – February 23, 2019 – On February 23, 2019, the first concrete span for the Whitemud LRT Bridge for the Valley Line Phase 1 was installed alongside the existing 75 Street bridge over Whitemud Drive near Mill Woods.

Here are some facts and figures on the LRT bridge span installed:

  • Two concrete spans make up the Whitemud LRT Bridge which will carry the Valley Line Light Rail Vehicles (LRVs) along 75/66 Street to and from Mill Woods.
  • The first span was erected over Whitemud Drive on Saturday, February 23.
  • Each span weighs nearly 600 tons and is more than 32 metres in length.
  • The two spans that make up the bridge are the eighth and ninth elevated spans, respectively, installed on the project thus far. The first concrete span was installed at the Davies Station site on December 17, 2018. Six more have been placed over the past several weeks on or near the Davies Station site adjacent to 75 Street, south of Wagner Road.
  • In total, the project consists of 45 elevated guideway spans. Most will be installed to accommodate the Davies Station elevated platform, while several will be installed near the Muttart Conservatory leading up to the Tawatinâ Bridge over the North Saskatchewan River.
  • The spans were moved into place using Mammoet’s Self-Propelled Modular Trailers (SPMTs). These multi-axle mobile platforms lifted the span from its storage location along Whitemud Drive, used a hydraulic jacking system to elevate the span to the correct height, and drove it to the install location. The span was then moved over top of the piers on which it would be set and was slowly lowered into position.
  • During the installation, the height, angle, and level of the lift were closely monitored by a team of more than a dozen operators and technicians.

 

Stay in Touch

Get the latest updates on progress reports, disruptions and Valley Line LRT news delivered straight to your inbox.

  • This field is for validation purposes and should be left unchanged.

If you are having trouble receiving the newsletter, kindly re-subscribe to TransEd’s mailing list and check your email privacy settings.