Temporary Closure of 75 Street Between Wagner Road and McIntyre Road

Notice, Vehicle

FOURTH UPDATE: Installation of the final concete span across 75 Street will happen on the night of June 14th from 9:00 p.m. to 6:00 a.m. and all lanes will be closed.

THIRD UPDATE: Installation of the concrete spans across 75 Street that was scheduled for the evening of Friday, May 31 will occur the night of Saturday, June 1.  Work will occur from 9:00 p.m. – 6:00 a.m and all lanes will be closed. 

The second installation will occur 9:00 p.m. – 6:00 a.m on Friday, June 14.  All lanes will be closed for this final placement.

SECOND UPDATE: Installation of the concrete spans across 75 Street will begin on the night of Thursday May 2. The following is a schedule of night time closures to accommodate the installation:

Thursday, May 2 (9:00 p.m. to 6:00 a.m.) – One southbound lane between Wagner Road and McIntyre Road will be temporarily closed

Friday, May 3 (9:00 p.m. to 6:00 a.m.) – All lanes on 75 Street between Wagner Road and McIntyre Road will be temporarily closed

Friday, May 17 (9:00 p.m. to 6:00 a.m.) – All lanes on 75 Street between Wagner Road and McIntyre Road will be temporarily closed

Friday, May 24 (9:00 p.m. to 6:00 a.m.) – All lanes on 75 Street between Wagner Road and McIntyre Road will be temporarily closed

UPDATE: This closure has been rescheduled for April 5, 2019. 75 Street between Wagner Road and McIntyre Road will be temporarily closed to accommodate the installation of a concrete girder near 75 Street. This will occur during night hours (9:00 p.m. to 6:00 a.m.) and will last for approximately three hours.

EDMONTON, AB – January 9, 2019 – Starting on or about February 1, 2019, 75 Street between Wagner Road and McIntyre Road will be temporarily closed to accommodate the installation of a concrete girder over 75 Street.

The closure will occur during off-peak hours (9:00 p.m. – 6:00 a.m.) on the nights of February 1st and 2nd. During this time, southbound traffic on 75 Street will be redirected via Wagner Road and northbound traffic will be rerouted via McIntyre Road.

To accommodate this work, the public will be impacted in the following areas:

  • During off-peak hours (9:00 p.m. – 6:00 a.m.) on the nights of February 1 and 2, 75 Street will be temporarily closed.
  • Southbound traffic on 75 Street will be redirected west via Wagner Road and northbound traffic will be rerouted west along McIntyre Road.
  • Pedestrian access will be maintained
  • Please visit https://www.edmonton.ca/ets/general-service-alerts.aspx for all ETS changes and updates

Alternate Routes:

  • Motorists travelling south on 75 Street will be rerouted via Wagner Road to 86 Street.
  • Motorists travelling north on 75 Street will be rerouted via McIntyre Road to 86 Street.
  • To avoid any delays, motorists can use 50 Street, 86 Street or 91 Street.

During this time please watch for, and observe, all traffic detours and direction of construction personnel.

Thank you for your understanding and patience as construction on the Valley Line LRT progresses. For the most current, up-to-date information in your area, please visit: http://transedlrt.ca/advisories/.

Please refer to the attached map for more details. For more information, visit our website http://transedlrt.ca/advisories or contact us via email at info@transedlrt.ca or by phone 780-224-0964.

 

Stay in Touch

Get the latest updates on progress reports, disruptions and Valley Line LRT news delivered straight to your inbox.

  • This field is for validation purposes and should be left unchanged.

If you are having trouble receiving the newsletter, kindly re-subscribe to TransEd’s mailing list and check your email privacy settings.